Bug 984265

Summary: MorphTo feature does not set predefined assignments and data input/output sets.
Product: [Retired] JBoss BPMS Platform 6 Reporter: Marek Baluch <mbaluch>
Component: jBPM DesignerAssignee: Tihomir Surdilovic <tsurdilo>
Status: CLOSED CURRENTRELEASE QA Contact: Marek Baluch <mbaluch>
Severity: medium Docs Contact:
Priority: unspecified    
Version: 6.0.0CC: kverlaen, smala
Target Milestone: ER4   
Target Release: 6.0.0   
Hardware: Unspecified   
OS: Unspecified   
Whiteboard:
Fixed In Version: Doc Type: Bug Fix
Doc Text:
Story Points: ---
Clone Of: Environment:
Last Closed: 2014-08-06 20:08:40 UTC Type: Bug
Regression: --- Mount Type: ---
Documentation: --- CRM:
Verified Versions: Category: ---
oVirt Team: --- RHEL 7.3 requirements from Atomic Host:
Cloudforms Team: --- Target Upstream Version:
Embargoed:

Description Marek Baluch 2013-07-14 09:14:51 UTC
Description of problem:
Some OOtB tasks like Email, Log, ... have predefined assignments and data input/output sets. These are filled out when such a tasks is added from the palette using D'n'D. However if such a task is added to the cavas using a normal task and the morph to feature then the predefined data assignments and data input/output sets are missing. 

How to reproduce:
1) add a Task to the canvas
2) morph it to Email for example
3) take a look at it's properties

Comment 1 Tihomir Surdilovic 2013-09-05 15:26:37 UTC
Custom workitem nodes should have not been in the Activities/Tasks morphing menu tobegin with. I have removed that. Fixed in designer master and 6.0.x branches.

Comment 5 Marek Baluch 2013-10-21 08:45:21 UTC
Verified on ER4