Created attachment 834888 [details] screencast Description of problem: When I try to import a BPMN2 process into an existing definition then the imported process is not considered as modification (it will not mark the editor as dirty) and save is not possible. Steps to Reproduce: 1. Open an existing process 2. Attempt to import another BPMN2 definition 3. Attempt to save the imported definition Actual results: Process contains no changes since last save. Expected results: The imported process is detected as a change and saved. Additional info: See screencast.
fixed in designer master and 6.0.x branches.
I can still reproduce this issue on ER6 using 'Steps to Reproduce'.
I cannot reproduce it. seems to work as expected.
Have you tried the ER6 build? If so - could you please attach/email_me a video showing the actions you are doing? Thank you @MB
Tested in bpmsuite-6.2.0.GA and this is now working.
Verified for 6.3.0 DR1