Description of problem: The tasks list provides a good overview what is being processed in the background. Also repo syncs are included. But it is unclear what triggered the repo sync. If it was e.g. started from a Sync plan or manual. It would be good to have an entry in the tasks lists that a Sync plan is being started and finished. Version-Release number of selected component (if applicable): How reproducible: Steps to Reproduce: 1. Create a hourly sync plan to sync a product 2. 3. Actual results: Only tasks that repos are sync, there is no reference included that it was started from a scheduled sync plan Expected results: Reference included that a sync plan is started&finsihed and which tasks below to the sync plan Additional info:
Since this issue was entered in Red Hat Bugzilla, the release flag has been set to ? to ensure that it is properly evaluated for this release.
Per 6.3 planning, moving out non acked bugs to the backlog
This is available in 6.2 where there is a parent task and sub tasks.