Complexity: Medium Date of First Response: 2008-08-21 11:18:58 project_key: SOA The platform needs a continuous integration machine. The set of both project and platform (integration/cross-project) tests that need to run needs to be determined. The results from the tests need to be made available.
A machine for building the SOA platform and running integration tests has been purchased and has arrived at the Brno office.
Machine has been installed and set up. Host name is: jawa05.englab.brq.redhat.com To do: Set up Xen dom0 and two xen domU clients
system set up, at the moment the CI handover involves a manual step, this will be automated once system is proved to be running correctly.
for some reason jira wouldn't let me resolve issue until closed and reopened