Description of problem: The icon shown in the activities column of the volume after remove-brick stop should reflect the actual status of the activity and should be in sync with the gluster CLI output. Version-Release number of selected component (if applicable): rhsc-2.1.2-0.24.master.el6_5.noarch How reproducible: Always Steps to Reproduce: 1. Go to Volumes tab and select a volume from the list 2. Start remove-brick by clicking the "Remove" menu option 3. Wait for sometime and click the "Stop" from drop down menu option in activities column from either bricks/volumes sub tab. Actual results: The activities column icon changes to stopped whereas the activities got finished by the time stop was fired. Expected results: If the activity got finished by the time stop was fired, the same should be reflected in volume and brick activities column as well. Additional info:
We should try to fix it, but if the infrastructure is not there to handle this situation, then we will remove this out of Corbett list. For the time being, i am keeping it in Corbett.
Activity column for remove-brick and GLUSTER CLI remove-brick output cannot be in sync because Gluster CLI says completed even if we stop the remove-brick operation after migration is completed. But in console we are marking this task as Aborted once the user calls retain after migration. One possible solution is that we can show the remove-brick summary status in remove brick status dialog as Aborted, if remove-brick is either stoped/retained.
As mentioned in my previous comment, i am removing this bug from the Corbett list. Current infrastructure is not capable of supporting this.
Closing as per comment 4