Description of problem: Any time one attempts to change the status of a day whether working or nonworker the application crahses when changes are applied. Version-Release number of selected component (if applicable): planner-0.12.1-2.1 How reproducible: Always Steps to Reproduce: 1. Start planner 2. Select "Project" pull down on menu bar 3. Select "Manage Calendars" on pull down 4. Click on any date on calendar 5. With "Set day type to:" radio selected, change the type to opposite of whatever it is. 6. Click "Apply" button Actual results: Application immediately crashes. Expected results: Day type should change without application crashing. Additional info:
This appears ok in RHEL-5 planner-0.14. If you wish this to be proposed for backporting to RHEL-4 you need to go through e.g. https://www.redhat.com/support/process/production/#howto